Answer:
Pc = 8294.4 units per week
Explanation:
Pc = U * A * ( N * sw * Hsh * Rp )/ n
Where
Pc = production capacity in terms of availability and utilization per week
U = utilization factor = 80% = 0.8
A = availability = 90% = 0.9
N = number of work centers = 8
sw = number of shifts per week = 10
Hsh = number of hrs per shift = 8
Rp = hourly production rate = 18 units /hr
n = number of distinct operations = 1 , same machine & part
So therefore,
Pc = 0.8 * 0.9 (8 * 10 * 8 * 18)/ 1
Pc = 8294.4 units per week