Answer:
$21,000,000
Explanation:
Ratio is used in allocating the research and development cost
This is the expression of relationship between two or more data showing the number of times one data contains or is contained in another data
Total research and development cost = $60,000,000
Revenue
Kentucky = $56,000,000
Arizona -= $ 100,000,000
Illinois = $84,000,000
Total = $240,000,000
Illinois allocation of research and development cost=
84,000,000/240,000,000*60,000,000 =$21,000,000
Answer:
<u>Using related diversification to achieve value by integrating vertically in order to acquire market power.</u>
Explanation:
First, let's understand what are the stages of a supply chain, they are:
- commodities
- manufacturing
- distribution
- retail
In this regard, we can see that Shaw Industries controls more than one stage of its supply, commodities and manufacturing chain, which characterizes vertical integration.
Therefore, the most appropriate alternative to the question is that the company gains a greater market gain with this strategy because it increases the management and quality control, by ensuring that the inputs and processes are in accordance with its standards, which guarantees a product of higher quality and consequently better positioned on the market.
Answer:
D) Project importance is enhanced by setting authority equal to that of functional departments.
Explanation:
A matrix organization is characterized by, multiple command system and overlapping of command, control and behavioral pattern.
Here, temporary project groups are created so as to handle short term projects. Personnel are drawn from functional department and their activities are controlled and coordinated by a project manager.
Once a project is completed, the structure is disbanded and the personnel return to their original departments i.e functional department.
During the project duration, a person is responsible and reports to two bosses, one being the project manager and secondly to the functional boss. Thus, under such a structure exists dual reporting.
Under matrix structure for project management, the project manager is not allowed to use resources exclusively for the project i.e like in project management. Rather, such a manager is required to share resources with the organization.
Answer:
freedom to make decisions
electronic mail and telephone
face-to-face discussions
Answer:
The correct answer is D.
Explanation:
Giving the following information:
The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1800 units, the actual direct labor cost was $48000 for 3000 direct labor hours worked.
We need to calculate the total direct labor variance, using two formulas:
Direct labor efficiency variance= (SQ - AQ)*standard rate
Direct labor efficiency variance= (1,800*2 - 3,000)*15= $9,000 favorable
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Direct labor rate variance= (15 - 48,000/3,000)*3,000= $3,000 unfavorable
Total direct labor variance= 9,000 - 3,000= $6,000 favorable