Answer:
A.- DECREASE
B.- DECREASE
C.- INCREASE
D.- INCREASE
E.- INCREASE
Explanation:
a. The discount rate increases
DECREASE the discoutn factors will be higher therefore, the present values lower.
b. The cash flows are in the form of a deferred annuity, and the total to $100,000. You learn that the annuity lasts for 10 years rather than 5 years, hence that each payment is for $10,000 rather than for $20,000
DECREASE Because the cashflow is generate on a longer period there is more exposure to discount rates.
c. The discount rate decreases
INCREASE The discount factor are lower. This situation is the opposite as (a)
d. The riskiness of the investment's cash flows <u>decreases</u>
INCREASE a lower risk derivates in lower cost of capital thus, lower iscount rates. This increase the present value of the cashflow.
e. The total amount of cash flows remains the same, but more of the cash flows are received in the earlier years and less are received in the later years.
INCREASE as most of the future cash flows are at the beginning they have less exposure to time value of money.
Answer:
USING 0% DISCOUNT RATE
PROJECT E
Year Cashflow [email protected]% PV
$ $
0 (23,000) 1 (23,000)
1 5,000 1 5,000
2 6000 1 6,000
3 7000 1 7,000
4 10,000 1 10,000
NPV 5,000
PROJECT H
Year Cashflow [email protected]% PV
$ $
0 (25,000) 1 (23,000)
1 16,000 1 16,000
2 5,000 1 5,000
3 4,000 1 4,000
NPV 2,000
Project A should be accepted
USING 9% DISCOUNT RATE
Year Cashflow [email protected]% PV
$ $
0 (23,000) 1 (23,000)
1 5,000 0.9174 4,587
2 6000 0.8462 5,077
3 7000 0.7722 5,405
4 10,000 0.7084 7,084
NPV (847)
PROJECT H
Year Cashflow [email protected]% PV
$ $
0 (25,000) 1 (23,000)
1 16,000 0.9714 15,542
2 5,000 0.8462 4,231
3 4,000 0.7722 3,089
NPV (138)
None of the projects should be accepted because they have negative NPV
Explanation:
The question requires the computation of NPV using 0% and 9%.
The cashflows of the two projects will be discounted at 0% and 9%.
The discount factors for each project can be calculated using the formula (1+r)-n. The cashflows of the projects will be multiplied by the discount factors to obtain the present values. NPV is the difference between present values of cash inflows and initial outlay.
Answer:
Instructions are below.
Explanation:
Giving the following information:
Job 765:
Direct material= $5,670
Direct labor= $3,500
Machine Hours= 27
Job 766:
Direct material= $8,900
Direct labor= $4,775
Machine Hours= 44
Job 765 produced 152 units, and Job 766 consisted of 250 units.
Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $200 per hour.
Costs sheet:
<u>Job 765:</u>
Direct material= 5,670
Direct labor= 3,500
Allocated overhead= 200*27= 5,400
Total cost= 14,570
Unitary cost= 14,570/152= $95.85
<u>Job 766:</u>
Direct material= 8,900
Direct labor= 4,775
Allocated overhead= 200*44= 8,800
Total cost= 22,475
Unitary cost= 22,475/250= $89.9
Answer:
Investors may invest a combined $50 million within a 12-month period.
Explanation:
According to the section, there are two pricing rates in Regulation A In the 1st Tier, for offering upto $20 million over a 12-month span and another 2nd Tier, for offerings upto $50 million over a 12-month period.
Therefore, as per the given situation the right answer is Investors are permitted to invest a combined $50 million over a 12-month period.