Answer:
$17.97 per unit
Explanation:
Using weighted average method, Equivalent units = Units that are completed during the period + Equivalent units in process at the end of period.
Equivalent units = 8,500 + 2,000*90%
Equivalent units = 8,500 + 1,800
Equivalent units = 10,300
Cost per equivalent unit for materials = (Beginning costs + Current costs) / Equivalent units
Cost per equivalent unit for materials = ($13,000 + $172,100) / 10,300 units
Cost per equivalent unit for materials = $185,100 / 10,300 units
Cost per equivalent unit for materials = $17.97 per unit
I think the answer is all of the above
The percentage of fixed costs in a company's cost structure.
I don't really understand your question but it is bad to pay only the minimum towards your credit card, interest rates will keep adding to your bill.
Answer:
True
Explanation:
If there is a more number of compounding periods within a year so it would result into the higher price of future value for lump sum investment in year 0 but the case would be adverse with the present value i.e there is less amount in the present value with regard to lumpsum amount i.e to be recieved in the future date
Hence, the given statement is true