Answer: 1. $690 (favorable)
2. $9045 (favorable)
Explanation: These can be computed as follows :-
Labor rate variance = Actual labor cost - (standard rate * actual hours)
= $139,380 - ( $20.1 * 6900 hours )
= $690 (favorable)
.
Labor efficiency variance = ( Actual hours - standard hours ) * (standard rate )
= [6900 hours - (1500 units * 4.3 hours) ] * ($20.1)
= $9045 (favorable)
The answer is D. All would be included as human resources
Answer:
C nag sa got ko sa yo yang C DAHIL SA VARIABLE
Answer:
Explanation:
The necessary adjusting entries at December 31 to record amortization required by the events above has been prepared.
It should also be noted that due to the goodwill having an indefinite life, no entry was made to amortize the goodwill.
It should be noted that the amortization expense was gotten as:
Annual amortization = $75,000/5
= $15,000
2015 amortization= $15,000 × 8/12months
= $15,000 × 2/3
= $30,000/3
= $10,000
Kindly check the attached file forthe adjusting entries
Answer:
The question is missing the options as given below:
A. mission statement
B. belief statement
C. goals pact
D. code of ethics
E. management pledge
The correct option is A,mission statement
Explanation:
The mission statement shows in summary form the vision,core values as well as statement of goals and objectives of an establishment.
Building the best product is the prioritized goal of Patagonia,since having the best product places it in the forefront in terms brand recognition,hence increased sales.
Core value here is ensuring no unnecessary harm is caused by way of injuries sustained in the course of pursuing its objectives.This implies that Patagonia is responsible corporate citizen in the area of complying with best practice in safety procedures.
The vision of the company is to implement solutions to environmental challenges through business inspiration.