Answer:
$5400 Favorable
Explanation:
Standard 2 hour at $15 per hour
Standard hours 2 hour per unit * 2900 units = 5800 hours
Total Standard cost = 5800 hours * $15 per hour = $87,000
Actual hours = 5100
Actual cost = $81600 / 5100 hours = $16 per hour
Variance = Standard - Actual
Labor hour Variance Favorable = 700 hours (5800 hours - 5100 hours)
Total Labor variance = $5400 ($87,000 - $81,600)
Answer:
a. Capture the reader's attention and interest.
Explanation:
To be able to make a request to someone persuasively, , it is very pertinent to lead the person to a point where such person can listen to you. This can only work in a context where you are very efficient in using story telling and other means of interaction that are capable of winning the persona interest and loyalty. Otherwise, you cannot have the person respond to your request.
Ice Cream. E<span>lasticity is higher when the good are luxuries and ice cream has </span>to actually be made.
Answer:
32
Explanation:
Using Formula
Cost + (Cost*Margin) = Selling Price
Cost is not known...
Cost (1 + Margin) = Selling Price
Cost = Selling Price / 1 + Margin
Here, Margin is 0.45 of cost and selling price is 46.4
Cost = 44.4 / 1.45
Cost = 32