Answer:
156.6%
Explanation:
Given:
Cosi Company's Incurred over head for the next period = $830,000
Expected labor hours = 53,000
Cost of labor = $10.00 per hour
Thus,
Total labor cost = 53,000 × $10.00 = $530,000
Now,
the Cosi Company's predetermined overhead rate will be calculated as:
Predetermined overhead rate = Incurred overhead / Total labor cost
on substituting the respective values, we get
Predetermined overhead rate = ( $830,000 / 530,000 ) = 1.566
or
Predetermined overhead rate = 1.566 × 100% = 156.6%