Answer:
Accept Project A and reject Project B
Explanation:
See the images to get the answer.
Decision: Required rate of return = 16% = Cost of capital.
If Internal rate of return (IRR) > the cost of capital = Accept the project.
If Internal rate of return (IRR) < the cost of capital = Reject the project.
From the basis of the formula, we can accept the project A because the IRR of Project A (19%) is higher than the cost of capital (16%). On the other hand, we can reject the project B because the IRR of Project B (14%) is smaller than the cost of capital (14%).
Answer:
It is more profitable to continue processing.
Explanation:
Giving the following information:
A company has inventory that cost $50,000. Its scrap value is $65,000. The inventory could be sold for $150,000 if manufactured further at an additional cost of $80,000.
Sell for scrap= 65,000 - 50,000= 15,000
Continue processing= 150,000 - 80,000 - 50,000= 20,000
Answer: 20.15%
Explanation:
The IRR is the discount rate that makes brings the Net Present Value to zero.
It can be solved for by various means including using Excel as shown in the attached file.
Year 0 -33790
Year 1 8,210
Year 2 9,890
Year 3 14,120
Year 4 15,930
Year 5 10,820
= IRR (-33,790
, 8,210
, 9,890
, 14,120
, 15,930
, 10,820
)
= 20.15%
Answer:
Total cost of transferred to finished goods inventory = $ 136,500
Explanation:
To value cost of transferred finished goods, we multiply the cost per equivalent unit of production (cost per EUP) by the the number of equivalent units (EUP) for each of the cost element.
So the value of the finished inventory, is determined as follows:
Value of inventory = cost per E.U.P × number of E.U.P
Direct Material = $5.00 × 21,000 =$ 105,000
Conversion cost = $1.50 × 21,000= $31,500
Total cost of transferred to finished goods inventory =
$ 105,000 + $31,500
= $ 136,500