Answer:
1,140 units
Explanation:
Note : The question requires us to use the weighted-average method. This method focuses on equivalent units of completed units and units still in process only.
Step 1 : Determine units completed and transferred
Units Completed = Beginning units + Units Started - Ending units
= 200 + 1,000 - 100
= 1,100 units
Step 2 : Calculate equivalent units of production with respect to conversion costs
Completed and transferred (1,100 x 100%) 1,100
Ending units (100 x 40%) 40
Total equivalent units of conversion costs 1,140
thus,
the equivalent units of productions for the period (using the weighted-average method) for conversion is 1,140 units.
Answer:
Letter a is correct. <em>Acceptable range of prices for any purchase situation.</em>
Explanation:
<u> The purchase decision</u> process is a systematic model that represents the rational or irrational steps a consumer goes through before making a purchase. These steps are related to solving needs, searching for information, evaluating similar alternatives, and post-purchase behavior.
The zone of acceptance is a step regarding the price range that the consumer is willing to pay for a particular product or service, and is influenced by each step of the consumer's buying decision.
Answer:
The answer is d. payment to hire a security worker to guard the gate to the factory around the clock.
Explanation:
Let re-visit to the concept of Fixed cost before applying to the questions.
Fixed costs are costs which are unchanged given changes in production level.
a. payment to a electric utility is not fixed cost because higher level of production required higher electricity consumption which leads to higher cost of electricity.
b. cost of raw material is not fixed cost because the higher the production level, the higher the raw material required for production.
c. wages to hire assembly line workers is not fixed cost because the higher the production level, the more workers required and the higher the wages will be.
d. payment to hire a security worker to guard the gate to the factory around the clock is fixed cost because regardless of the production level, the security worker will work for the same amount of time and receive the same level of payment as his workload is much likely to remain the same.