As a licensed foster mom, the answer is F. All of above
Answer:
Instructions are listed below
Explanation:
Giving the following information:
For the purchase option:
Buying price= $22 per unit.
For the make option:
Weekly rental payment of $30,800
The firm also has to hire five operators to help make product A. Each operator works eight hours per day, five days per week at the rate of $14 per hour.
The material cost for the make option is $15 per unit of product A.
A) We need to find the number of units that makes the unitary fixed costs= $7
Weekly rental= 30800
Direct labor= ($14*8 hours*5workes)*5 days= 2800
Total fixed costs= $33,600
Unitary fixed costs= total fixed costs/ Q
7=33600/Q
Q= 4800 units
B) Now Q= 6600
Buy= 6600*22= $145,200
Make= 6600*15 + 33600= $132,600
Answer:
Option A Risks affecting the business operations and potential outcomes of an organization's activities.
Explanation:
The reason is that the business risk are those risks that has potential to increase the cost of the company or decrease the revenue of the organization. So here the misstatement will not increase the cost of the organization and the only risk that increase the cost or decrease the revenues is the poor performance of the organization's activities and operations. So the right option which doesn't talks about misstatements is option A.
Below are the resources:
<span>Logistical, human, technical, financial
</span>
A SWOT analysis is an organized arranging strategy that assesses those four components of an association, venture or business wander. A SWOT examination can be completed for an organization, item, place, industry, or individual. It includes determining the target of the business wander or extend and distinguishing the inside and outside variables that are great and negative to accomplish that goal.
Answer:
Standard price= $6.1
Explanation:
Giving the following information:
The quantity of direct materials used 3,800 lbs. Actual unit price of direct materials $6 per lb. Units of finished product manufactured 1,820 units Standard direct materials per unit of finished product 2 lbs.
Direct materials quantity variance—unfavorable $976 Direct materials price variance—favorable $380.
Direct material price variance= (standard price - actual price)*actual quantity
380= (SP - 6)3,800
6.1= standard price
Direct material quantity variance= (standard quantity - actual quantity)*standard price
976= (1820*2 - 3,800)*SP
6.1= standard price