Answer: D) gain the attention of the consumer.
Explanation:
The first and foremost thing is marketing is to gain the attention of the consumer. This is why Adverts usually start with something eye catching and then move on to explain the product.
All other steps in the marketing process including development of brand awareness cannot be implemented if the consumer's attention is not gained.
The first and foremost goal of marketing in simple terms therefore is to first grab their curiosity then gain their attention.
It can be said that Fruitlicious demonstrates Efficiency
<h3><u>
Explanation:</u></h3>
Efficiency correlates to the quality of your profession, which might involve building manufacturing with more limited waste, utilizing fewer resources or consuming smaller money. Improved efficiency can impede productivity and vice versa. Obtaining the correct sequence of productivity and efficiency assists you optimize your yield while reducing losses.
Added means to look at efficiency is the amount of gained hours of great quality productive product sorted by the number of work hours possible in a day. Essentially to expand manufacturing efficiency you want to create added output in the equivalent amount of time
Death or happiness or even sadness or maybe life or a happy feeling
The market mechanism benefits society by ensuring that: <span>scarce resources are channeled into products most desired by society
Market mechanism determines which products stays or go by relying purely on the force of supply and demand. If the products are desired by the customers, the producer will always keep up with the demand in order to rake in the potential profit.</span>
Answer:
a) Process A is the bottleneck of the process
b) Hourly capacity = 60 / bottlenecktime = 60/25 = 2.4 units / hour
Explanation:
Part 1 is processed at A for 15 minutes and then at B for 10 minutes.
Thus part 1 take 15 + 10 i.e. 25 minutes two complete both processes
Part 2 is processed at C for 20 minutes.
Output from B and C i.e. part 1 and 2 respectively are fed to process D where the time taken to assemble is 15 minutes
Thus looking at the given data,
Part 1 takes longer time i.e. 25 minutes to reach process C compared to part 2 i.e. 20 minutes
So bottleneck occurs at process A and B because it takes maximum time i.e. 25 minutes
a) Process A is the bottleneck of the process
b) Hourly capacity = 60 / bottlenecktime = 60/25 = 2.4 units / hour