Answer:
Break-even point in units= 770
Explanation:
Giving the following information:
Selling price= $500
Unitary variable cost= $260
Fixed costs= $184,800
<u>To calculate the break-even point in units using the mathematical equation, we need to use the following formula:</u>
<u></u>
Net income= unit contribution margin*x - fixed costs
x= number of units
0= (500 - 260)*x - 184,800
184,800/240 = x
770=x
<u>Now, under the unit contribution margin method:</u>
Break-even point in units= fixed costs/ contribution margin per unit
Break-even point in units= 184,800/240
Break-even point in units= 770
Answer:
The correct answer is the second option: Extensive training and careful precautions are necessary to avoid accidents, injuries and illness.
Explanation:
To begin with, all of the other options are describing the fact that the laws that regulate the workplace environment are no necessary or state that are enough. That is why that in the option chosen it is stated that it is absolutely necessary to have extensive training in the areas of work, specially those who are danger, and to take precautions around all so that the accidents can be prevented and the injuries will no happen as well as the illnesses. Therefore that the right to a safe workplace is accurately described by that statement.
The executing and controlling phases of a project usually overlap because project work takes place during the executing phase. A project manager monitors the status of a project and takes a corrective action as work is being performed. There are five phases of project management namely; conception and initiation, planning, execution, performance/monitoring, and project close.