Answer: Pandemic: awful. Vaccine: useful; get it. Masks: not really required, your still breathing your air, just through tiny gaps in fabric.
Explanation:
just my opinion.
Answer: $44,000
Explanation:
Equivalent units for materials in this scenario would be:
= Units completed and transferred out + Normal spoilage + Ending work in process
= 33,000 + 3,000 + 8,000
= $44,000
Answer:
True
Explanation:
Critical-Chain
This was introduced or originated by Eli Goldratt in 1997. Its aim is to challenges conventional project management approaches and absolute dependence on TOC principles. The idea of what to change or eliminated is the largely rooted behaviors that is common with the traditional project management practices. It is very multitasking anf it is the longest string of reliance that occur on the project.
Critical- Chain Approach
This approach simply covers project network as it ca be limited by both resource and technical reliance/dependencies. each type of limitations can create task reliance.
The Summary of Critical Chain Approach
1.) use Aggressive but Possible Times (ABPT) for task durations
2.) identify the critical chain by accounting for resource dependencies
3.) use buffer management to track project progress etc.
Answer:
E. Sales, accounting, and manufacturing and production.
Explanation:
Order fulfillment first takes place in the Sales department - where the Sales team makes known to the customer the products and services available. then the human resources selects talent to help with the production and manufacturing. Accounting function helps determine the cost.
Answer:
Yes it does. Yes it does.