Answer: $721 Unfavorable
Explanation:
The following can be deduced from the question:
Actual hours = 3690 hours
Standard hours = 3620 hours
Standard rate per hour = ($14000 + $27200) / 4000
= $41200 / 4000
= $10.30 per hour
Therefore, the overall variable overhead efficiency variance for the month is calculated as:
= (Actual Hours - Standard Hours) × Standard rate per hour
= (3690 - 3620) × $10.30
= 70 × $10.30
= $721 Unfavorable
Answer: $66.90 per unit
Explanation:
Cost that would be avoided is:
= Direct materials + Direct cost + Variable manufacturing overhead + part of fixed manufacturing overhead
= 20.80 + 26.50 + 6.90 + (36.10 - 31.40)
= $58.90
If the outside supplier commits to 59,000 units a year, the company should not pay more than:
= (Number of units supplied * Avoidable cost + contribution margin on other product (opportunity cost) ) / Number of units supplied
= (59,000 * 58.90 + 472,000) / 59,000
= $66.90 per unit
Answer:
make sure workers aren't slacking and helping customers
Answer:
With respect to this lease, for 2018 Ogleby should record interest expense of $57,058 and depreciation expense of $107,225. The right answer is c
Explanation:
According to the given data we have the following:
PV of lease=$750,578
Annual payment=$180,000
Rate of interesr=10%
The interest expense would be calculated as follows:
Interest expense = ( PV of lease - Annual payment ) * Rate of interest
Interest expense = ( $750,578 - $180,000 ) * 10%
Interest expense = $57,058
Therefore, With respect to this lease, for 2018 Ogleby should record interest expense of $57,058 and depreciation expense of $107,225.