Answer:
<u>cost of goods manufactured schedule</u>
Raw Materials ($9,180 + $55,020 - $17,480) $46,720
Direct Labor $51,740
Manufacturing overheads :
indirect labor $6,510
factory insurance $4,700
machinery depreciation $4,380
machinery repairs $1,990
factory utilities $3,740
miscellaneous factory costs $1,980
Add Opening Work In Process $5,670
Less Closing Work In Process ($7,610)
Cost of goods manufactured $119,800
Explanation:
Cost of goods manufactured schedule shows a summary of results (cost) obtained from manufacturing activity during the production period.
Answer:
Assuming that you can only choose one answer, the most suitable one would be (A) Chris designs models to make traffic flow better, which enables Brian to get to his company’s warehouse faster.
Explanation:
This answer is correct because Chris is a traffic planner – thus he merely designs the traffic flow, he does not create it, thus making answer (D) incorrect. Though (B) is true, it doesn’t relate to Chris’ career, making it false as well. As for (C), the answer is not correct because Chris doesn’t design the maps of the state, he only designs the traffic flow.
This is the presentation of the income statement of
Builtrite in order to compute the net income:
Sales $700,000
Less: COGS $280,000
Gross Profit $420,000
Less: Operating expenses ($700,000 x 25%) $175,000
Dividends
expense $25,000
Capital loss $70,000 $270,000
Total $150,000
Add: Dividend income $40,000
Capital gain $55,000 $95,000
Net income $245,000