Answer:
The correct answer is D.
Explanation:
Giving the following information:
The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1800 units, the actual direct labor cost was $48000 for 3000 direct labor hours worked.
We need to calculate the total direct labor variance, using two formulas:
Direct labor efficiency variance= (SQ - AQ)*standard rate
Direct labor efficiency variance= (1,800*2 - 3,000)*15= $9,000 favorable
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Direct labor rate variance= (15 - 48,000/3,000)*3,000= $3,000 unfavorable
Total direct labor variance= 9,000 - 3,000= $6,000 favorable
The demand for ben & jerry's ice cream will likely be more price elastic than the demand for dessert.
<h3>What is the elasticity of Demand?</h3>
When all other conditions are equal, the elasticity of demand is a concept in economics that quantifies how responsive consumers are to shifts in the quantity desired as a result of a price adjustment. In other words, it demonstrates the number of things consumers are willing to buy as the cost of those products rises or falls.
By dividing the percentage change in quantity by the percentage change in price during a specific period, the elasticity of the demand formula is computed. It appears as follows:
Elasticity is defined as % change in quantity / % change in price.
The quantity demanded as a result of a percentage change in a product's price is hence the measure of demand elasticity. Demand can be elastic or inelastic depending on whether products' demand is more responsive to price fluctuations. When a product's demand is flexible, the desired quality is extremely responsive to price variations. When a product's demand is rigid, the desired quality does not adapt well to price variations.
Therefore, The demand for ben & jerry's ice cream will likely be more elastic than the demand for dessert.
For more information on the elasticity of demand, refer to the following link:
brainly.com/question/23301086
#SPJ4
Answer:
Its "Customers get a new piece of jewelry every three months.
Explanation:
The first option, never tells what the customer gets in return.
Sorry this answer is two weeks late. Happy Thanks Giving!
Answer:
C) person who works well alone
Explanation:
Answer:
1. Requires substantial resources.
2. produces different numbers than a traditional system.
3. Is costly to maintain.
Explanation:
Activity-based costing (ABC) system is a method of accounting assigns the total cost of activities such as manufacturing overhead costs and indirect costs necessary to produce a product or provide a service.
Basically, an activity-based costing (ABC) system is focused on the cost drivers associated with the respective activities, which are responsible for cost to be incurred. The cost drivers are activities such as direct labor, purchase order, machine use etc.
<em>Hence, an activity-based costing system requires substantial resources, produces different numbers than a traditional system and is costly to maintain.</em>