Answer:
hope it's help you ok have a good day
Answer: c. $1,650 unfavorable
Explanation:
The direct labor rate variance shows the difference between the cost of direct labor that the company thought it would incur vs what it actually incurs for the period.
Formula is:
Direct labor rate variance = Actual cost of direct labor - Standard cost of actual hours of direct labor
= Actual hours * (Actual cost - Standard cost)
= 5,500 * (24 - 23.70)
= $1,650 unfavorable
Unfavorable because the actual cost incurred was more than the cost anticipated.
Answer:
$444.42
Explanation:
For computing the saving amount, first need to calculate the economic order quantity, total cost etc
The economic order quantity is
where,
Annual demand is
= 774 packaging crates × 12 months
= 9,932 crates
And, the carrying cost is
= $12 × 34%
= $4.08
= 363.37 crates
Now the total cost is
= Annual ordering cost + Annual carrying cost
= Annual demand ÷ Economic order quantity × ordering cost per order + Economic order quantity ÷ 2 × carrying cost per unit
= 9,288 ÷ 363 × $29 + 363 ÷ 2 × $4.08
= $742.02 + $740.52
= $1,482.54
Now the total cost in case of 774 packing crates is
= Annual ordering cost + Annual carrying cost
= Annual demand ÷ Economic order quantity × ordering cost per order + Economic order quantity ÷ 2 × carrying cost per unit
= 9,288 ÷ 774 × $29 + 774 ÷ 2 × $4.08
= $348 + $1,578.96
= $1,926.96
So, the annual saving cost is
= $1,926.96 - $1,482.54
= $444.42
The answer is: A.Position a worker to signal you when operating a vehicle in reverse gear without audible forward alarm
When operating vehicle in reverse gear, the operator cannot always see whether the worker who gives the signal able to see the moving vehicles or not.
Which is why an audible sound for moving vehicles is needed so the other workers could notify the location of your vehicles and avoid themselves from being crushed.
Answer:
$50,875
Explanation:
The computation of the present value is shown below:
Given that
NPER = 5 × 2 = 10
RATE = 10% ÷ 2 = 5%
PMt = $0
FV = $82,870
The formula is shown below:
= -PV(RATE;NPER;PMT;FV;TYPE)
After applying the above formula, the present value is $50,875
Hence, the present value is $50,875
We simply applied the above formula so that the correct value could come
And, the same is to be considered